Maple Steel Sdn Bhd v Bina Mahir Sdn Bhd

Maple Steel Sdn Bhd sued Bina Mahir Sdn Bhd for RM216,018.72 in unpaid subcontractor fees for a Klang Komuter Station project. Bina Mahir counterclaimed RM202,000 in liquidated damages for alleged delays. The Sessions Court ruled in favor of Maple Steel, awarding the full claim amount plus interest and costs, while dismissing Bina Mahir's counterclaim.

Overview

Case Number

BA-A52NCvC-554-10/2020

Case Type

Civil - Construction contract dispute

Court

Sessions Court, Shah Alam

Coram Judge

Related Proceedings

High Court
Court of Appeal

Subject Matter

construction lawcontract lawliquidated damages