Maple Steel Sdn Bhd v Bina Mahir Sdn Bhd
Maple Steel Sdn Bhd sued Bina Mahir Sdn Bhd for RM216,018.72 in unpaid subcontractor fees for a Klang Komuter Station project. Bina Mahir counterclaimed RM202,000 in liquidated damages for alleged delays. The Sessions Court ruled in favor of Maple Steel, awarding the full claim amount plus interest and costs, while dismissing Bina Mahir's counterclaim.
Overview
Case Number
BA-A52NCvC-554-10/2020
Case Type
Civil - Construction contract dispute
Court
Sessions Court, Shah Alam
Coram Judge
- Ishak bin BakrDelivered Judgment
Related Proceedings
High Court
Court of Appeal
Subject Matter
construction lawcontract lawliquidated damages