Mazmimala Binti Mashur & 47 Others v Symphony Hills Sdn. Bhd.
48 plaintiffs sued Symphony Hills Sdn. Bhd. for liquidated agreed damages (LAD) due to delayed delivery of vacant possession in the Serene Heights housing project. The plaintiffs claimed delays ranging from 177 to 668 days. The court determined key legal questions under Order 14A of the Rules of Court 2012, ultimately dismissing the plaintiffs' claim based on the Federal Court's decision in Obata-Ambak Holdings Sdn Bhd v. Prema Bonanza Sdn Bhd & Other Appeals [2024] 8 CLJ 519.
Overview
Case Number
BA-22NCvC-453-11/2021
Case Type
Civil - Housing development dispute
Court
High Court of Malaya, Shah Alam
Coram Judge
- Elaine Yap Chin GaikDelivered Judgment
Related Proceedings
High Court
BA-22NCvC-453-11/2021
High Court of Malaya at Shah Alam
Subject Matter
housing developmentliquidated damagescontract law