MLR

WA-22C-51-06/2019

High Court in Malaya Kuala Lumpur
Civil
30 August 2024
judgment delivered

Case WA-22C-51-06/2019 involves a construction dispute between Eastmont Sdn Bhd (Plaintiff) and Mega Planner Jaya Sdn Bhd (Defendant) regarding outstanding payments for substructure works completed for serviced apartments in Setapak, Kuala Lumpur.

The High Court allowed the Plaintiff's claim for RM7,230,492.14 and dismissed the Defendant's counterclaim for liquidated damages and rectification costs.

The case centered on issues of mutual termination, final account statements, variation orders, and limitation periods for counterclaims.

Background

The dispute arose from a construction contract where the Plaintiff was appointed to carry out substructure works for a project in Setapak. The contract was mutually terminated in December 2013, leading to disagreements over outstanding payments, variation orders, and claims for defective works.

Issues

  • Whether the Statement of Final Account dated 28.10.2014 is deemed final and conclusive
  • Whether the Defendant has to pay the amounts claimed in the Statement of Claim
  • Whether the Defendant's claim for LAD has exceeded the limitation period
  • Whether the Defendant is estopped from raising issues of rectification works and LAD
  • Whether there exists any right to claim for damages after mutual termination
  • Whether the Defendant is entitled to claim for rectification costs
  • Whether the Defendant is entitled to set off/claim LAD
  • Whether the Defendant is entitled to claim indemnity for late delivery claims
  • Whether the Defendant is entitled to set off payments made to G-Pile

Holdings

  • Statement of Final Account dated 9.1.2019 deemed final and conclusive
  • Plaintiff entitled to claim for outstanding payments and variation orders
  • Defendant's LAD claim time-barred under Limitation Act 1953
  • Defendant estopped from raising rectification works and LAD claims
  • Mutual termination extinguished Defendant's rights to claim damages
  • Defendant failed to prove Plaintiff caused damage to piles

Reasoning

  • The Defendant's delay in disputing the Final Account made it conclusive
  • The Plaintiff successfully proved its claims for payments and variation orders
  • The Defendant's counterclaim for LAD was filed beyond the limitation period
  • The Defendant's conduct showed no intention to pursue LAD claims after mutual termination
  • The Defendant failed to provide expert evidence on alleged pile damage

Significance

Clarifies the effect of mutual termination on parties' rights to claim damages and the importance of timely dispute of final accounts in construction contracts.

Precedential Value

Establishes guidance on handling construction disputes involving mutual termination and limitation periods for counterclaims.

Judgment

Reasoning

The Court found that while the Defendant had various defenses and counterclaims, it failed to pursue them in a timely manner and could not prove the Plaintiff's liability for alleged defective works. The mutual termination and subsequent conduct of parties were crucial in determining their rights.

Main Findings

  • Final Account became conclusive due to lack of timely dispute
  • Plaintiff proved entitlement to payment for works and variations
  • Defendant's counterclaims were time-barred or inadequately proven
  • Mutual termination extinguished certain rights to claim damages

Orders Made

  • Plaintiff's claim allowed for RM7,230,492.14
  • Defendant's counterclaim dismissed
  • Interest awarded at 5% per annum from 10.6.2019
  • Costs of RM80,000 ordered against Defendant's contributory

Keywords

construction contract
mutual termination
final account
variation orders
liquidated damages
rectification works
limitation period
set-off
burden of proof

Case Details

Case ID: WA-22C-51-06/2019

Case Date: 30 August 2024

Case Status: judgment delivered

Court Information

Court: High Court in Malaya Kuala Lumpur

Location: Kuala Lumpur, Federal Territory of Kuala Lumpur

Type: High Court

Jurisdiction: Civil

Presiding Judge

Name: Aliza Sulaiman

Position: Judge

Parties

Eastmont Sdn Bhd

plaintiff

ID:

Mega Planner Jaya Sdn Bhd

defendant

ID:

Case Information

Case Type: contract

Monetary Value: RM 7,230,492.14

Governing Laws:

  • Limitation Act 1953 Section 6 (1, a)
    Limitation period for actions founded on contract
  • Evidence Act 1950 Section 101
    Burden of proof
  • Rules of Court 2012 Section Order 59
    Costs
  • Contracts Act 1950 Section 63
    Novation, rescission and alteration of contracts

Cause of Action & Relief Sought

Cause of Action:

    Relief Sought:

      Interlocutory Applications

      TypeFiled ByDateOutcome
      Set Aside JIDdefendant17 May 2023Allowed

      Key Events

      Letter of Award issued to Plaintiff

      Contract sum of RM26,000,000.00

      Mutual termination of contract agreed

      Notice of Termination issued

      Architect issued instructions to vacate site

      Statement of Final Account issued

      Valued at RM19,215,148.17

      Final Statement of Account signed

      By Plaintiff and Quantity Surveyor

      High Court judgment delivered

      Plaintiff's claim allowed, Defendant's counterclaim dismissed

      Judgment

      Date: 30 August 2024

      Outcome: Plaintiff's claim allowed partially, Defendant's counterclaim dismissed

      Reasoning:

      Court found Plaintiff proved its claims while Defendant's counterclaims were time-barred or inadequately proven

      Additional Information

      Related Cases:

      • BA-28NCC-97/2019
      • BA-28PW-144-05/2023
      • BA-22NCC-82-06/2020

      Remarks:

      Complex construction dispute involving mutual termination, final accounts and counterclaims. Defendant's appeal pending.